A does a work in 12 days and B does it in 6 days. With C joining them, they can finish the work in 3 days. In how many days can C alone finish the work?

English বাংলা
PREVIOUSLY ASKED IN:
WBPSC Miscellaneous Preliminary 2023

Answer

12 days

Explanation

A's 1-day work = \\( \\frac{1}{12} \\), B's 1-day work = \\( \\frac{1}{6} \\). A, B, and C together finish in 3 days, so their 1-day work = \\( \\frac{1}{3} \\). Therefore, C's 1-day work = \\( \\frac{1}{3} - (\\frac{1}{12} + \\frac{1}{6}) \\) = \\( \\frac{1}{3} - \\frac{3}{12} \\) = \\( \\frac{1}{3} - \\frac{1}{4} \\) = \\( \\frac{1}{12} \\). Since C does \\( \\frac{1}{12} \\) of the work in 1 day, C alone will take 12 days to complete the work.

Key Points

  • > Total work is considered as 1 unit in the fractional method.
  • > Work done by A and B in 1 day = \\( \\frac{1}{12} + \\frac{1}{6} = \\frac{1}{4} \\).
  • > Work done by all three in 1 day = \\( \\frac{1}{3} \\).
  • > C's daily work = Total - (A+B) = \\( \\frac{1}{3} - \\frac{1}{4} = \\frac{1}{12} \\).
  • > LCM method is faster: LCM of 12, 6, 3 is 12 (Total Work).
  • > Efficiencies: A=1, B=2, (A+B+C)=4. Thus C=1 unit/day.
  • > Time taken by C = 12/1 = 12 days.

Additional Information

LCM Method for Time & Work

PersonDaysTotal Work (LCM)Efficiency (Units/Day)
A121212/12 = 1
B61212/6 = 2
A+B+C31212/3 = 4
C (Alone)12124 - 3 = 1

Memory Tips

  • Efficiency Rule: Always convert days into per-day efficiency. Subtraction gives the exact efficiency of the missing person.
Mathematics Arithmetic Medium