PREVIOUSLY ASKED IN:
PSC Miscellaneous Prelims 2018
Answer
5 days
Explanation
Y can complete the whole work in 12 days. So, Y's 1 day's work is 1/12. Since Y worked for 9 days, the work completed by Y = 9 × (1/12) = 3/4 of the work. The remaining work is (1 - 3/4) = 1/4. X can finish the whole work in 20 days. Therefore, the time taken by X to finish the remaining 1/4th of the work is = 20 × (1/4) = 5 days.
Key Points
- > Total work is considered as 1 unit.
- > Y's efficiency = 1/12 work per day.
- > Work done by Y in 9 days = 9/12 = 3/4.
- > Remaining work = 1 - 3/4 = 1/4.
- > X completes 1 unit in 20 days.
- > Time taken by X = Remaining work × X's total time = 1/4 × 20 = 5 days.
- > LCM Method: Total work = LCM(20, 12) = 60 units. Y does 5 units/day, X does 3 units/day.
Additional Information
LCM Method Breakdown
| Person | Days | Efficiency (Units/Day) | Total Work (LCM) |
|---|---|---|---|
| X | 20 | 3 | 60 |
| Y | 12 | 5 | 60 |
Memory Tips
- LCM Magic Trick: Y does 5 units/day. In 9 days, Y completes 45 units. Remaining work = 60 - 45 = 15 units. Since X does 3 units/day, X will finish the rest in 15 ÷ 3 = 5 days.
